The Operative Ledger, by DB3 Wire
Circle $39

The Ledger ยท EXAMINATION

Who Pays for the Cloud: Data Centers and Your Power Bill

Utilities are building plants and lines for data centers at a pace the grid has not seen in decades. Whether households help pay depends on rules most customers have never read. North Carolina's are being written now.

By Nov 9, 2026

The roof of a data center
The roof of a data center. Photo: Rsparks3, CC0, via Wikimedia Commons

75%

Minimum share of reserved capacity a large NC customer pays (Duke settlement)

85%

Same floor in Ohio (AEP) and Virginia (Dominion)

$28.92 vs. $333.44 per MW-day

PJM capacity price, 2024 to 2025 vs. 2027 to 2028

About 5,100 of 5,250 MW

Data centers' share of PJM forecast peak growth

About $20M

Yearly revenue from NC ending the data center power tax break

On Oct. 6, Duke Energy filed a settlement with the North Carolina Utilities Commission. Amazon, Google, Microsoft and the Public Staff, the state agency that represents utility customers, signed on. It sets the terms for customers that want 50 megawatts or more of power around the clock, which in practice means data centers.

One number in it decides a lot. A large customer must pay for at least 75% of the capacity it reserves, whether it uses that power or not, according to the filing. In Ohio and Virginia, the same floor is 85%.

That gap is where your bill comes in.

Why the floor matters

A utility builds for the load it expects. If a data center reserves 500 megawatts and then uses less, or leaves, the plants and lines are already paid for. Someone covers the difference. A minimum demand charge, a bill floor tied to reserved capacity, decides how much of that risk stays with the data center.

Under the North Carolina settlement, as filed:

  • Customers of 50 MW or more at an 80% load factor, or any load of 150 MW or more, sign 10 to 15 year contracts.
  • They pay at least 75% of contract demand.
  • Leaving early costs notice-period charges plus 25% of remaining minimum payments.
  • They post collateral and pay upfront for facilities built only for them.
  • They post a letter of credit covering the estimated cost of transmission network upgrades, reduced once they reach 75% of contract demand.
  • Deals signed before June 1, 2026 are exempt.

The commission has not ruled. The proposed start date is Jan. 1, 2027.

Nick Jimenez of the Southern Environmental Law Center, which opposes the deal, told WFAE that under the terms "the rest of us are stuck holding the bag." Eddy Moore of the Southern Alliance for Clean Energy said departing customers "could pay only 25% of remaining electricity costs for years." Will Scott of the Environmental Defense Fund called it "a step in the right direction," but said it "fails to do the same for new power plants."

How other states wrote the rule

StateRuleWhat large customers commitStatus
North Carolina (Duke)SettlementAt least 75% of contract demand; 10 to 15 year termsAwaits NCUC
Virginia (Dominion)New rate class for loads of 25 MW+85% of distribution and transmission demand; 60% of generation demand; 14-year contractsOrdered Nov. 2025; effective Jan. 1, 2027
Ohio (AEP)Data center tariffAt least 85% of subscribed capacity; up to 12 yearsApproved July 2025
Georgia (Georgia Power)PSC ruleLoads over 100 MW pay upstream generation, transmission and distribution costs; contracts up to 15 years; minimum billsApproved Jan. 2025
Indiana (I&M)Settlement70 MW+; 12-year minimum term; exit fee for cuts above 20%Filed Nov. 2024
Texas (ERCOT)SB 675 MW+; at least a $100,000 study fee; financial security; remote curtailment for new loadsLaw June 2025; rules in progress

Sources: the Duke filing, Cardinal News, POWER, the Georgia PSC, Utility Dive and Bracewell.

North Carolina also changed the tax side. The state repealed the sales tax exemption on electricity bought by data centers, effective July 7, 2026, according to the Department of Revenue. WUNC reported that brings in about $20 million a year. Virginia's data center tax break, on equipment and software rather than electricity, cost about $1.6 billion in fiscal 2025, up 118%, The Register reported, citing the state's annual financial report.

The bill you can already see

North Carolina's Duke territory is not in PJM, the grid operator for 13 states and Washington, D.C. But PJM shows what happens when demand outruns supply. Its capacity price, what it pays plants to be available three years out, went from $28.92 per megawatt-day for 2024 to 2025 to $333.44 for 2027 to 2028, according to Utility Dive and PJM. Total auction costs went from $2.2 billion to $16.4 billion.

PJM said data centers account for about 5,100 of the 5,250 megawatts of growth in its forecast peak. An E3 analysis cited by Lawrence Berkeley National Laboratory attributes about half of the capacity price rise to data centers.

The case that data centers pay their way

The industry's argument is owed full strength. Josh Levi of the Data Center Coalition said, "The data center industry is committed to paying its own way for the power it uses." An E3 report the coalition commissioned found "no quantitative evidence to date that data centers have historically been subsidized by other customers," Axios reported.

There is evidence on that side too. An Electric Power Research Institute analysis, summarized in the Berkeley Lab review, found residential rates fell about 0.4% for every 10% of data center load growth from 2015 to 2024. More customers can spread fixed costs.

The other side points to the record of how those costs were assigned. Harvard's Electricity Law Initiative reviewed nearly 50 regulatory proceedings and concluded the public is "paying the energy bills of some of the largest companies in the world."

Berkeley Lab's August 2026 review lands in the middle: the effect on household rates depends on how much spare capacity a system has, how exposed it is to markets, and how the tariff is written. That last part is a choice regulators make.

What to watch on your bill

  1. The capacity or generation line. In PJM states it tracks the auction.
  2. Rider lines, the separate charges for things like transmission or fuel. New grid spending often shows up there between rate cases.
  3. Rate case notices from Duke or Dominion, which state the residential increase in dollars per month.
  4. The NCUC ruling on Duke's settlement, which decides how much of the grid cost stays with data centers.
  5. Fuel and storm charges, which swing with gas prices whatever data centers do.

What we owe each other

Nobody has to choose between the cloud and the light bill. The question is who carries the risk when a forecast is wrong. A family on a fixed income cannot walk away from its utility. A data center with a 15-year contract and a 25% exit fee can.

Watch the NCUC docket, E-7 Sub 1329 and E-2 Sub 1380, for the ruling. Watch Georgia's newly elected Public Service Commission majority, which Atlanta News First reported plans an affordability review that includes data center costs.

Sources

  1. Duke Energy large-load tariff settlement
  2. Duke Energy agreement on large-load tariff
  3. Duke proposal fails to hold data centers accountable
  4. Repeal of data center electricity exemptions
  5. NC budget rolls back data center tax exemption
  6. Regulators approve Dominion rate increase
  7. AEP Ohio data center tariff approved
  8. PSC data centers rule
  9. Georgia's flipped utility commission targets power bills
  10. I&M large-load settlement
  11. Texas Senate Bill 6
  12. PJM 2027/2028 auction results
  13. PJM capacity auction prices
  14. Large load literature review, August 2026
  15. Extracting profits from the public
  16. E3 energy white paper
  17. Data center report on electricity costs
  18. Virginia data center tax breaks

The Ledger Brief

Money, power and opportunity, in plain English. Free, in your inbox.

Not financial advice. This is general reporting on utility rates, not a recommendation about any security or investment. News and analysis. Not financial advice.